5106.303-1-90 Requirements for amended justifications.

(a) The contracting officer shall amend a justification and obtain the required approvals when any of the following occur prior to award of the contract action:

(1) The dollar value of the prospective contract action increases beyond the authority of the previous approving official.

(2) A change in the competitive strategy further reduces competition.

(3) A change in requirements affects the basis for the justification.

(b) The Senior Procurement Executive (SPE) approves all amendments to justifications previously approved at the SPE level, except when the basis for the amended justification supports a lower approval level per FAR 6.304.

(c) Prepare all amended justifications as required in 5106.303-2-90(c)(3).