5117.9005 JOC ordering officers.

(a) Appointment. A “JOC ordering officer” appointment is authorized, but is only required when the Contracting officer will not be executing all task orders. Appointments of ordering officers under each JOC must be minimized. The JOC ordering officer shall be obtained in accordance with AFARS 5101.603-1, The Contracting officer is the appointing authority for each individual job order that is within the JOC ordering officer authorities. The requiring activity may recommend JOC ordering officers. The JOC ordering officer shall be appointed by letter similar to that in 5153.303-2 Sample ordering officer appointment. (see 5101.602-2-92 Ordering officer appointments.), tailored for JOC.

(b) Training. All JOC ordering officers must receive specific training and orientation from the responsible contracting office at least annually and must document completion in PCF. This training must cover policy and procedures for the operation of a JOC and shall specifically address the ordering officer’s authority, limitations, and responsibilities, including ethics, conflict of interest, and potential pecuniary liabilities. JOC ordering officers shall, at a minimum, meet contracting activity COR training requirements.

(c) Authorization and limitations.

(1) JOC ordering officers are authorized to sign task orders on behalf of the Government between the micro-purchase threshold for acquisitions of construction and the Simplified Acquisition Threshold (SAT) as long as the value of the non-pre-priced item(s) does not exceed five percent of the total order to include contract modifications.

(2) The HCA may authorize JOC ordering officers to sign task orders of greater value than SAT. However, the delegated authority may not exceed the thresholds specified in 10 U.S.C. 2805(c) and may only be authorized when the HCA determines, in writing it is necessary to realize the benefits of a JOC, and provided that –

(i) adequate management controls are in place (e.g., Contracting officer oversight);

(ii) adequate training is provided;

(iii) the Contracting officer approves; and

(iv) the value of any non-pre-priced item(s) does not exceed 5 percent.

(3) JOC ordering officers may execute modifications to existing task orders provided that -

(i) the Contracting officer delegates explicitly this authority in the JOC ordering officer appointment letter;

(ii) the absolute value of the order as modified does not exceed the ordering officer’s authority; and

(iii) pricing is accomplished by using the JOCPB.

(iv) modifications shall be limited to changing quantities of JOCPB items in the existing order unless the Contracting officer signs an in-scope determination.

(4) JOC ordering officers must notify the Contracting officer immediately of any modifications. The Contracting officer shall execute any modification outside of paragraph 3 above.

(d) Responsibilities. JOC ordering officers--

(1) Are responsible for ensuring that all proposed JOC project descriptions and task orders express the Government’s actual requirements, validated in accordance with the requiring activity’s procedures;

(2) Must obtain concurrence from the Contacting officer that sufficient capacity exists on the JOC before issuing of a task order;

(3) Must obtain a valid Purchase Request and Commitment (PR&C) from resource management to ensure that adequate and proper funds are available for the project before issuing an order and/or modification;

(4) Must notify the Contracting officer of any additional bonding requirements associated with new orders or changes in the value of existing orders;

(5) As the principal point of contact for technical and engineering issues, must respond to requests for technical clarification from the JOC contractor, documenting both the request and the response, and conduct the joint pre-proposal site survey, assuring that the contractor is provided access to all required facilities, plans, and other documents required for full knowledge of the scope and conditions of the required job;

(6) For orders estimated to exceed the JOC ordering officer’s signature authority, the JOC ordering officer shall conduct an initial evaluation of contractor proposals; may be authorized to solicit such proposals and clarify and negotiate units and quantities of pre-priced tasks; and shall assist the Contracting officer, as requested, in negotiations, and resolution of variances between the IGE and the contractor’s proposal;

(7) Must maintain a contract file in PCF and complete contract documentation for each order and modification executed, including a record of all related correspondence and actions taken before award of the order and in the order administration phase; and

(8) Is responsible, along with a COR, if appointed, for assisting the Contracting officer in technical monitoring of the contractor’s performance of orders issued under a JOC to include --

(i) Monitoring compliance with the SOW and schedule;

(ii) Ensuring contractor or supplier compliance with the clause at FAR 52.225-5, Trade Agreements (Nov 2023);

(iii) Ensuring compliance with the Wage Rate Requirements (Construction) statute (40 U.S.C. Chapter 31, Subchapter IV, formerly known as the Davis Bacon Act, subpart 22.4);

(iv) Assessment and validation of percentage of completion for progress payment purposes;

(v) Recommending to the Contracting officer changes to existing orders, beyond the ordering officer’s authority;

(vi) Documenting and quickly reporting to the Contracting officer systemic or recurring problems in contractor performance;

(vii) Prioritization of orders when required (in coordination with the requiring activities), provided no increase in cost is involved;

(viii) Submitting performance evaluation reports (see AFARS 5136.201), as applicable; and

(ix) Providing to the requiring activity documents required for continuing customer responsibilities (e.g., as-built drawings and warranties).