932.501-2 Unusual progress payments.
(a)(3) For DOE, the Head of the Contracting Activity shall forward all requests which are considered favorable, with supporting information, to the DOE Senior Procurement Executive, who, after coordination with the Chief Financial Officer, Headquarters, will approve or deny the request. For NNSA, the NNSA Senior Procurement Executive will coordinate with the NNSA Chief Financial Officer before approving or denying the request.
(d) Requests for unusual progress payments will not be considered as a handicap or adverse factor in the award of a contract; provided the bid or proposal is not conditioned on approval of such request.