552.246-72 Final Inspection and Tests.

552.246-72 Final Inspection and Tests.

As prescribed in 546.312 , insert the following clause:

Final Inspection and Tests (Sep 1999)

The Contractor shall give written notice to the Contracting Officer at least 10calendar days before the date the work will be completed and ready for final inspection and tests. Final inspection and tests will begin within 10calendar days after the date specified in the Contractor’s notice unless the Contracting Officer determines that the work is not ready for final inspection and so informs the Contractor.

(End of clause)